Al-Akhbar newspaper reported today: "Welcome to Qleiaat Airport... which operates only during the day, and only when weather conditions permit." This is neither a joke nor an attempt to belittle the "achievements" of Prime Minister Nawaf Salam and Minister of Public Works and Transport Fayez Rassamny, but rather an unfortunate reality resulting from the mismanagement of those in charge and their rush toward achieving illusory accomplishments that conceal commercial deals behind them.
According to Al-Akhbar's information, the Directorate General of Civil Aviation granted Qleiaat Airport a conditional operating certificate for only 90 days, starting November 15 and ending February 13, 2027. The certificate allows limited civil aircraft movement, subject to strict restrictions confining operations solely to daylight hours and favorable weather conditions. This is due to the complete absence of instrument landing systems (ILS) and navigational equipment... as well as non-compliance with any international standards. This raises the question of why there is a rush to inaugurate the airport on Independence Day, November 22, despite its lack of readiness.
Clearly, some officials in the Lebanese state are prioritizing the satisfaction of their egos over public safety, which they do not mind endangering through an unjustified rush. In this context, Al-Akhbar learned that the Prime Minister told a delegation from Akkar that history would record two achievements for him: the decision on disarmament and the opening of Qleiaat Airport, adding that the opening would bring an exceptional economic revival to the North, aside from attracting American interest that even surpasses Washington's interest in Hezbollah's weapons.
The inaugural flight from Qleiaat Airport is expected to depart on Independence Day for Cairo Airport in Egypt. However, the takeoff schedule is not yet finalized, as the conditional license is tied to fulfilling essential operational requirements within a one-week deadline, under penalty of license revocation.
Yet, the sheer number of required repairs makes completing them within the set timeframe an impossible task. Most notably, these include repairing the runway—which suffers from cracks and road subsidence—and rehabilitating its shoulders, establishing an airport operations program and an emergency plan, and repairing meteorological observation systems and data transmission systems. Ironically, the Minister seeks to operate the airport in a primitive manner, treating it as if it were an amusement park or a private backyard playground, as the airport even lacks night lighting and an instrument landing system—the fundamental device for ensuring aviation safety—making landing impossible both day and night if weather conditions deteriorate. When he and those tasked with managing the airport were asked about the scenario of weather suddenly worsening while a plane is mid-air, and whether the pilot should proceed to land on the runway or return to the point of departure, none of them could answer, instead placing the responsibility squarely on the pilot.
It does not stop there. Even "Dar Al-Handasah," the consultancy firm tasked with supervising the execution of the works, opposed opening the airport in its current state on the grounds that it is not yet ready, especially given that the runway lacks the required safety conditions, rendering it unsafe for aircraft takeoff or landing. Consequently, "Dar Al-Handasah" withdrew its name from the conditional certificate out of the company's keenness to protect the Lebanese state, its facilities, and its reputation. It appears the consultant cares more about the state than its own officials do, as Rassamny insists on the opening, with the inaugural flight set to launch amid media fanfare to cover up these scandals. Notably, what is unfolding is taking place under the cover of false information regarding readiness and exceptional works being relayed to Salam.
On the other hand, some believe that flights will not take off on November 22 due to the difficulty of completing what is required within the specified deadline, or that it will not be long before flights are suspended once again. The airport has not obtained a license to operate as an international airport, and it is unlikely to accommodate large aircraft or have any country send its planes there. All that the operating company, "Sky Lounge Services," has been permitted to do under the conditional certificate is receive small aircraft only, accommodating no more than eighty passengers. Here, a dispute erupted among the partners themselves over the economic feasibility of investing in a "daytime" airport that could shut down at any hour if the sky turns overcast or in the event of rain, with aircraft movement restricted to just four flights per day! Consequently, "Ibex Air Charter," owned by Ahmad Al-Hajj, has begun reconsidering its calculations, according to informed sources, given the losses it will incur due to the airport's current condition. In this context, the inaugural flight will mark the first of expected losses, with Al-Hajj chartering a plane operating in Africa to transport its passengers; sources indicate this will entail financial costs for him without any return, while Al-Hajj will be unable to open booking/registration for an airport that is unready and fails to meet standards.