It’s been two years of closures and detours around the I-696 construction in Oakland County. But come early December, the eastbound side of the freeway will welcome eastbound traffic again.

However, expect more construction on I-696 in the spring when work to repair the stretch between I-75 and Dequindre starts.

“There’s a lot of last-minute punch list items, just like when you’re working at a home, that still have to be done,” said Diane Cross with MDOT.

What’s happening on I-696 now

MDOT rebuilt eastbound I-696 between M-10 and I-75 last year. Over the summer, crews moved to rebuild the westbound lanes.

Cross says one of the main remaining steps is removing temporary pavement markings that won’t be needed once all lanes are reopened.

“Right now it’s empty, and we’re trying to get it ready to hopefully reopen by no later than early December is where it’s looking right now,” Cross said. “So that’s going to be a wonderful holiday gift.”

Drivers should still expect some construction activity near Orchard Lake Road, MDOT says.

More I-696 work planned in the spring

MDOT says construction will return in the spring on both eastbound and westbound I-696 between I-75 and roughly Dequindre.

“We do come back in the spring on 696 east and west between 75 and roughly to Dequindre,” said Diane Cross with MDOT. “We have to rebuild that part of the freeway that we could not do because we needed that 75 interchange to be part of the detour. So once we start working between 75 and the Dequindre, we’ll still keep two lanes open so there’s no massive detour like what we’ve had for the last couple of years. But drivers are not done seeing construction on 696 until the end of ’27.”

I-94 construction: what drivers should know

MDOT is also continuing a long-term project on I-94, covering a 13-mile stretch east of I-275 to west of Michigan Avenue.

“We are down to two lanes both directions sharing the true westbound side,” Cross said. “So we’re tearing up eastbound in parts. We’re doing bridge work in parts. We’re doing concrete pavement repair. We’re doing ramps. We’re doing a lot of things on the eastbound side.”

MDOT says drivers should plan for the I-94 impacts to continue through and well past the holiday season, and the project is expected to last another couple of years.

Getting to Detroit Metro: suggested route

If you’re headed to Detroit Metro Airport, MDOT recommends taking I-275 to Eureka Road.

Safety reminder for drivers

Cross also emphasized work-zone safety, urging drivers to slow down and stay alert.

“You’re protected by thousands of pounds of steel, metal, glass — airbag, seatbelt. You’re in good shape,” Cross said. “The people on the side of the road have a hard hat and a vest and a barrier wall and hoping that drivers are doing what they should be doing.”